Wyndhamvale Quarry Plant Project Report Brisbane Address low res

Brightwater Delivered an EPC 600t/hr aggregate crushing plant for The Barro Group in Wyndhamvale, Victoria, Australia.

 

 
7576 Ocean Gold Globe Project Report Brisbane Address low res

Gold Processing Plant

Oceana Gold Globe, West Coast, New Zealand

In mid 2006 Brightwater were awarded contracts for the structural, mechanical and piping supply and installation scope for the new gold processing plant at Oceana Gold’s Globe Progress Gold Mine at Reefton, New Zealand.
Brightwater had previously been awarded the fabrication contract for all tanks, chutes and processing vessels which included a 20m diameter clarifier

 
BWE11388 SMP Project Report Oceana Gold NZ Address low res

SMP Project

Oceana Gold, Macraes Flat, Otago, New Zealand

Oceana Gold constructed a gold processing plant to extract ore concentrate at the Globe Progress Mine, in Reefton. This plant was due to be commissioned and in production in the first quarter of 2007.
The ore concentrate was to be transported by road/rail/road to be further processed at the Macraes Flat Processing Plant.